
ACO Technologies: £46,937 of grid electricity avoided
245 kWp rooftop system. 183.6 MWh generated and 94.7% used on site from December 2025, when monitoring began, to 4th August 2026.

A 1.1 MWp array removed and reinstated around a 30,000 m² roof replacement, with all 215 strings tested and signed off.
The solar array at Jaguar Land Rover's Whitley site had outlived the roof beneath it. Water had been getting in for months and the roof had to be replaced, so the whole array had to come off first and go back on afterwards.
There were no drawings or records for the system, and its condition was unknown: 4,518 panels and 1.1 MWp across a 30,000 m² roof. The work had to fit the 5-month roof replacement, with as little disruption as possible to JLR's engineering operations below.
We surveyed and mapped the whole system before any physical work began, so that every component was accounted for and the array was documented for the first time.
We stripped the array, then reinstated it over five months in step with the roof replacement, adjusting our schedule around the other contractors on site.
We replaced degraded clamps, cabling and MC4 connectors, and put right earlier faults such as unearthed frame sections and damaged cables.
We inspected and tested the reinstated array to BS EN 62446-1:2016 and signed it off on 9th January 2024 as an NICEIC registered contractor. All 215 DC strings were tested after reinstatement, and every one was operational, with earth continuity verified. The array had been baselined in July 2023, before it came off, and was validated again afterwards. The tested array is 1,074.57 kWp.
Two things were outside our work: seven of JLR's 72 existing inverters were faulty at handover, four of them locked off, and six damaged panels were left disconnected on the roof on the main contractor's instruction.
4,518 panels
removed and reinstated across 72 inverters
215 DC strings
tested after reinstatement, every one operational, with earth continuity verified
5 months
to reinstate the array, in step with the roof replacement





“Potentia Engineering excelled in refurbishing our Jaguar Land Rover solar PV system, overcoming challenges with precision. Their meticulous planning seamlessly integrated with our operations, ensuring optimal performance. Highly recommend their expertise.”
Delivered by the Potentia Engineering team

245 kWp rooftop system. 183.6 MWh generated and 94.7% used on site from December 2025, when monitoring began, to 4th August 2026.

76.26 kWp across two buildings, 186 panels, with a 15.36 kWh battery, installed in under three weeks.
Send an address, a drawing or a half-hourly data file. We respond within one working day.
