Holy Apostles' C of E Primary School: 10.92 kWp installed in the summer holidays
A 10.92 kWp system on the school's flat roof, with nothing through the membrane, and solar panels with battery storage on six almshouses.

Principal contractor for 0.5 MWp across 50 sites in the council's solar programme, delivered around the school calendar.
Gloucestershire County Council is putting solar on the roofs of its school buildings. We are one of two suppliers appointed to its £2M solar PV framework, which runs from 17th February 2025 to 16th February 2028, and 50 of the schools are ours. The programme is meant to cut carbon emissions across the council's estate and to bring measurable savings to individual schools, which manage their own energy budgets.
Every school is different. Each roof, electrical supply and planning position needs its own solution, and the work has to fit around the school calendar.
We deliver each school from start to finish: feasibility, then structural, electrical and asbestos surveys, then a design for that roof and its orientation.
We make the network operator applications (G98 or G99) and manage the grid connections across the programme's supply points.
Installation is planned around the school terms. Each system is MCS compliant and handed over with its operation and maintenance documents and its monitoring.
We report carbon and financial savings for the whole programme against the council's sustainability targets.
Schools in the programme include Tredworth Junior, Lakeside Primary, Longlevens Infant and Junior, Castle Hill Primary, Churchdown Parton Manor, Grangefield Primary, Archway School and Stroud Valley Primary. At Maidenhill School the council funded the original array and the school paid for extra panels under the same contract terms, installed over the October 2026 half term.
We also delivered Cirencester Fire Station under the same framework.





“Gloucestershire County Council’s Solar for Schools Programme is delivering solar PV across maintained schools throughout the county, helping schools generate clean electricity on site, reduce their reliance on grid energy and lower long-term energy costs. Potentia is supporting the County Council in the delivery of the programme, which forms part of its wider commitment to reducing carbon emissions and improving the sustainability of its school estate. The programme demonstrates how investment in renewable technology can deliver meaningful environmental and financial benefits for schools, while supporting Gloucestershire’s longer-term decarbonisation ambitions.”
Delivered by the Potentia Engineering team

A 10.92 kWp system on the school's flat roof, with nothing through the membrane, and solar panels with battery storage on six almshouses.

A 26 kWp solar system with 20 kWh of battery storage on the council's Community Hub, which generated 25 MWh in 2025, 51% of the building's electricity use.
Send an address, a drawing or a half-hourly data file. We respond within one working day.