Drone pass over the solar array on the Porta Romana factory roof

Commercial, Farnham

Porta Romana: two buildings and a battery in under three weeks

76.26 kWp across two buildings, 186 panels, with a 15.36 kWh battery, installed in under three weeks.

The brief

Porta Romana wanted to cut its energy bills and carbon footprint and rely less on the grid, as part of its work towards B Corp certification.

Its pattern of use made that a balancing act: the system had to meet the site's needs, with any surplus put to good use. The work was a retrofit across two buildings on a busy working site.

What we did

We analysed Porta Romana's energy use, with power logging surveys for battery storage and EV charging, and assessed the structure of the roofs and the viability of the system.

The array spans two separate roofs at Porta Romana's Northbrook premises near Farnham, with battery storage positioned on the Dairy side. We installed 186 Eurener 410 W panels across the two buildings. The first has a 36 kW Solis inverter. The second has a 25 kW Solis inverter and a 10 kW Solis hybrid inverter connected to a 15.36 kWh PureDrive battery, four 3.84 kWh modules that can be expanded later. The battery stores surplus generation for the evening and for peak times.

The system's annual output is sized to the site's annual consumption. Not all of it is used on site, but it cuts the site's reliance on the grid.

We installed the system between 17th September and 2nd October 2024, in under three weeks.

The EV chargers followed as a separate job in January 2025: 66 kW of EV charging for Porta Romana.

Results

76.6 MWhForecast

generated a year

Basis
Potentia's design forecast in its proposal to Porta Romana

£15,200Forecast

saved on energy bills in the first year

Basis
Potentia's design forecast in its proposal to Porta Romana

£3,300Forecast

from selling surplus power to the grid in the first year

Basis
Potentia's design forecast in its proposal to Porta Romana

Evidence

“We’re thrilled with the outcome of this project. Potentia Engineering’s expertise and professionalism made the entire process seamless, from planning to execution. Their team worked with us closely to design and implement a solution that not only meets our current energy needs but positions us well for the future as we work toward B Corp certification. We’re excited about the energy savings and the environmental impact this project will deliver.”

Ali MilamManaging Director, Porta Romana

Delivered by the Potentia Engineering team