ACO Technologies: £46,937 of grid electricity avoided
245 kWp rooftop system. 183.6 MWh generated and 94.7% used on site from December 2025, when monitoring began, to 4th August 2026.

Engineering consultant from the design stage: our modelling showed a smaller transformer would do, and we installed a 92.2 kWp rooftop system.
The Natural Dispensary was building new premises in Stroud, with a rooftop solar system planned from the start.
The grid connection specified for the building included a larger transformer than it needed, sized on worst-case assumptions about export. That would have added to the cost of the connection.
We were engaged as engineering consultant while the building was still being designed. We modelled the building's generation and consumption in detail and showed that a smaller transformer would do.
On that basis we negotiated a revised grid connection agreement with the network operator, without export limitation or supply restrictions.
We installed the 92.2 kWp system on the new roof between 20th April and 1st May 2026, set up to match the site's operating loads behind the meter.





Delivered by the Potentia Engineering team

245 kWp rooftop system. 183.6 MWh generated and 94.7% used on site from December 2025, when monitoring began, to 4th August 2026.

A 1.1 MWp array removed and reinstated around a 30,000 m² roof replacement, with all 215 strings tested and signed off.